The mission aims to ensure every household has access to a tap with assured water supply and a sewerage connection, and to increase the amenity value of cities through greenery and well-maintained open spaces.
In the news, the Uttar Pradesh government plans to provide sewer connections to 416,000 urban homes under AMRUT 2.0. Of a planned 1,751.52 km sewer network, 827.41 km is already built, and eight sewage treatment plants (201 million litres per day) and 16 water treatment plants (326.25 million litres per day) are under construction.Hindustan
Atal Mission for Rejuvenation and Urban Transformation 2.0 (AMRUT 2.0): quick facts
- Launch date
- AMRUT 2.0 was launched on 1 October 2021 for five years, FY 2021-22 to FY 2025-26.
- Parent ministry
- Ministry of Housing and Urban Affairs (MoHUA), Government of India.
- Total outlay
- Total indicative outlay of ₹2,99,000 crore, including Central outlay of ₹76,760 crore for five years.
Key facts
| Launch date | AMRUT 2.0 was launched on 1 October 2021 for five years, FY 2021-22 to FY 2025-26.PIB |
|---|---|
| Parent ministry | Ministry of Housing and Urban Affairs (MoHUA), Government of India.PIB |
| Total outlay | Total indicative outlay of ₹2,99,000 crore, including Central outlay of ₹76,760 crore for five years.PIB |
| Coverage | Universal water supply through functional taps to all households in all statutory towns; sewerage/septage management in 500 cities of the first phase.PIB |
| Uttar Pradesh target | 416,000 urban homes to get sewer connections in Uttar Pradesh, as announced by the state government (story).Hindustan |
Key features and how it works
- Universal coverage of water supply through functional taps to all households in all statutory towns across the country.PIB
- Coverage of sewerage and septage management in the 500 cities covered in the first phase of AMRUT.PIB
- Central funds are allocated to states and UTs for AMRUT 2.0 projects and administrative and office expenses. Puducherry's plan under the original AMRUT scheme is fully funded through the Central share.PIB
- Projects are planned through State Annual Action Plans (SAAP), a consolidated plan of city-level Service Level Improvement Plans of all proposed AMRUT cities in a state.
Static GK
- Ministry of Housing and Urban Affairs (MoHUA): the Union ministry that runs AMRUT 2.0 and sanctions Central funds to states and UTs.PIB
- State Annual Action Plan (SAAP): consolidated plan of all city-level SLIPs of AMRUT cities in a state; the basis for project approval.
- City Mission Management Unit (CMMU): unit set up at each city to assist the Urban Local Body with staff and technology (first phase design).
Comparison
AMRUT 2.0 vs Swachh Bharat Mission-Urban 2.0 vs AMRUT (first phase)
| Basis | AMRUT 2.0 | Swachh Bharat Mission-Urban 2.0 | AMRUT (first phase) |
|---|---|---|---|
| Focus | Water supply and sewerage/septage coverage | Garbage-free cities through source segregation, door-to-door collection and scientific waste management | Sewerage networks and water supply for urban transformation |
| Launch | 1 October 2021 | 1 October 2021 | June 2015 |
| Period | Five years, FY 2021-22 to FY 2025-26 | Five years | Not stated in sources opened |
| Implementing body | Ministry of Housing and Urban Affairs | Ministry of Housing and Urban Affairs | Ministry of Urban Development (per Wikipedia) |
Achievements
- Uttar Pradesh has built 827.41 km of its planned 1,751.52 km sewer network and is building 8 sewage treatment plants.Hindustan
Challenges
- Sewer lines are built, but treatment and connection to homes must keep pace, otherwise untreated wastewater still reaches rivers and ponds.
- Regional imbalance is likely: large states such as Uttar Pradesh need far bigger allocations than small states and UTs.
Way forward
- Support weaker ULBs with technical staff and planning assistance, drawing on the first phase's proposal for City Mission Management Units to assist ULBs with staff and technology.
- Converge AMRUT 2.0 with Swachh Bharat Mission-Urban 2.0 and other schemes so that water, sewerage and waste management work together.Hindustan
Timeline
23 November 2026
Uttar Pradesh plans sewer connections for 416,000 urban homes under AMRUT 2.0, with 827.41 km of a planned 1,751.52 km sewer network already built and treatment plants under construction.
Read it in full1 October 2021
AMRUT 2.0 launched for five years, FY 2021-22 to FY 2025-26, with a Central outlay of ₹76,760 crore.PIB
June 2015
AMRUT (first phase) launched by Prime Minister Narendra Modi to build sewerage and water supply in urban areas.
Every new topic on this subject is added here automatically.
Frequently asked questions
When was AMRUT 2.0 launched?
AMRUT 2.0 was launched on 1 October 2021 for five years, from FY 2021-22 to FY 2025-26.PIB
What is the total outlay of AMRUT 2.0?
The total indicative outlay is ₹2,99,000 crore, including a Central outlay of ₹76,760 crore for five years.PIB
Which ministry runs AMRUT 2.0?
The Ministry of Housing and Urban Affairs runs AMRUT 2.0.PIB
GS paper mapping
- GS-2Government policies and interventions for development in sectors such as health, education, and urban development
- GS-3Infrastructure: water supply, sanitation and urban infrastructure
- GS-3Environment: pollution control and protection of rivers and water bodies