Super Current Affairs

Programme

China-Kyrgyzstan-Uzbekistan Railway: complete guide

An under-construction 530 to 532 km trilateral railway linking Kashgar (China), Kyrgyzstan and Andijan (Uzbekistan), promoted under the Belt and Road Initiative to create a new east-west corridor for freight.

Updated: 26 November 20261 topic

The China-Kyrgyzstan-Uzbekistan railway (CKU railway) is an international railway being built by China, Kyrgyzstan and Uzbekistan. It runs from Kashgar in Xinjiang through the Torugart Pass, Makmal and Jalal-Abad in Kyrgyzstan to Andijan in eastern Uzbekistan.

The line is meant to give western China a new east-west transport corridor into Central Asia and, through connecting networks, to the Middle East and Europe. The three governments promote it as part of the Belt and Road Initiative, and it avoids Russia for freight moving west.

Plans date to the 1990s, when China, Kyrgyzstan and Uzbekistan signed a memorandum in 1997. The project stayed largely stalled for about three decades over financing, route choice, track gauge and geopolitics, which is why its construction status is a current news topic.

China-Kyrgyzstan-Uzbekistan Railway: quick facts

Linked initiative
Belt and Road Initiative
Termini
Kashgar (China) to Andijan (Uzbekistan), via Kyrgyzstan
Legal basis
Trilateral intergovernmental agreement signed on 6 June 2024

Key facts

Linked initiativeBelt and Road InitiativeHindustan
TerminiKashgar (China) to Andijan (Uzbekistan), via Kyrgyzstan
Legal basisTrilateral intergovernmental agreement signed on 6 June 2024
Estimated costAbout ₹44,000 croreHindustan
Estimated completion in 202622% (estimated completion in 2026, per the latest update; operations targeted for 2031)Hindustan
Structures28 tunnels, 50 bridges, 20 stations; about 120 km through bridges and tunnelsHindustan

Key features and how it works

  • Route: runs west from Kashgar to the Torugart Pass, then through the Tian Shan mountains via Makmal to Jalal-Abad, joining the Uzbek network towards Andijan.
  • Division of work: China builds on its own territory, Uzbekistan upgrades railway infrastructure within Uzbekistan, and a joint project company in Kyrgyzstan handles financing, construction and later operation of the Kyrgyz section.
  • Track gauge: standard gauge (1,435 mm) from China to Makmal and broad gauge (1,520 mm) from Makmal westwards, so a break-of-gauge and transshipment complex is planned at Makmal.
  • Engineering: the mountainous Kyrgyz section is the most demanding part, with long tunnels and bridges, which is the main reason for the high cost.
  • Freight role: from Andijan, cargo could connect westwards towards Europe through Turkmenistan, Iran and Türkiye, potentially shortening journeys to some markets by about 900 km.Hindustan

Static GK

  • Belt and Road Initiative: a global infrastructure and economic development strategy pursued by China since 2013, covering projects in more than 150 countries.
  • China-Kyrgyzstan-Uzbekistan Railway Company: the joint project company in Kyrgyzstan that finances, builds and will operate the Kyrgyz section.
  • Track gauges: China uses 1,435 mm standard gauge; Kyrgyzstan and Uzbekistan use the 1,520 mm broad gauge inherited from the Soviet railway system.

Comparison

CKU railway vs Boten-Vientiane railway (Laos-China Railway)

BasisChina-Kyrgyzstan-Uzbekistan railwayBoten-Vientiane railway
StatusUnder construction; construction launched 27 December 2024Opened 3 December 2021
LengthAbout 530 to 533 km (Wikipedia); story says 532 km422 km
Track gauge1,435 mm standard (Kashgar-Makmal), 1,520 mm (Makmal-Andijan)1,435 mm standard gauge
CostAbout ₹44,000 crore (story)US$5.965 billion (Wikipedia)
Operator / ownerChina-Kyrgyzstan-Uzbekistan Railway Company (Kyrgyz section)Laos-China Railway Company Limited (LCR)

Achievements

  • The trilateral intergovernmental agreement of 6 June 2024 gave the project a legal and institutional framework after decades of talks.
  • Construction of three major tunnels began on 29 April 2025, and the project has moved into active construction.

Challenges

  • Mountain terrain of the Tian Shan: the Kyrgyz section requires tunnels and bridges, with about 120 km of the line passing through these structures.Hindustan
  • Track gauge mismatch: the break-of-gauge at Makmal requires transshipment facilities and adds operating cost.
  • Financing and route disputes delayed the project for nearly three decades. Published length estimates changed as the project progressed, with the final engineering plan reported at approximately 530-533 km.

Way forward

  • Handholding of the joint project company so that the Kyrgyz section can recover its costs and stay financially viable in operation.
  • Convergence with Central Asian and European corridors, including the Trans-Caspian route, so that freight gains from Makmal and Andijan are realised.

Timeline

  1. 25 November 2026

    Construction is underway on the 532 km line, with 22% completion targeted for 2026 and operations targeted for 2031.

    Read it in full
  2. 29 April 2025

    Construction of three major tunnels begins.

  3. 27 December 2024

    Ceremonial launch of construction at Tosh-Kutchu, Jalal-Abad Region, attended by Kyrgyz President Sadyr Japarov.

  4. 6 June 2024

    Trilateral intergovernmental agreement signed, providing for a joint project company in Kyrgyzstan.

  5. 2023

    The three parties agree to proceed with the Torugart, Makmal and Jalal-Abad route.

  6. 1997

    China, Kyrgyzstan and Uzbekistan sign a memorandum on the railway.

Every new topic on this subject is added here automatically.

Frequently asked questions

Which countries does the CKU railway connect?

It connects China, Kyrgyzstan and Uzbekistan, running from Kashgar in Xinjiang to Andijan in Uzbekistan.

When was the trilateral agreement for the CKU railway signed?

The three governments signed the intergovernmental agreement on 6 June 2024.

GS paper mapping

  • GS-2India and its neighbourhood relations; bilateral and regional groupings and agreements involving India and/or affecting India's interests
  • GS-2Effect of policies and politics of developed and developing countries on India's interests
  • GS-3Infrastructure: energy, ports, roads, airports, railways

Sources

Every fact on this page was checked against these pages.

  1. Hindustan

Latest current affairs on this subject