The 2026 guidelines provide a framework for scientific mine planning and closure, with defined scrutiny and approval timelines and a one-month reimbursement timeline for mine closure works. They complement the existing statutory framework and avoid redundant compliance requirements.PIB
The guidelines recognise underground coal gasification as a mining method and make the 2026 underground gasification mining plan guidelines an integral part of the framework.PIB
Guidelines for preparation of Mining Plan and Mine Closure Plan for Coal and Lignite Mines, 2026: quick facts
- Issuing ministry
- Ministry of Coal
- Date of issue
- 20 November 2026
- Commencement
- 30 days from the date of issue
Key facts
| Issuing ministry | Ministry of CoalPIB |
|---|---|
| Date of issue | 20 November 2026PIB |
| Commencement | 30 days from the date of issuePIB |
| Escrow reimbursement | Reimbursement for mine closure works from the escrow account reduced to one month from receipt of claim, with provision for test-check of claimsPIB |
| Five-yearly claim verification | Scope of agencies verifying five-yearly claims for escrow withdrawal widenedPIB |
| Underground coal gasification | Recognised as a mining method; the 2026 underground gasification mining plan guidelines are made an integral part of this frameworkPIB |
Key features and how it works
- Outcome-oriented framework: sets the approach for systematic and scientific mine planning and mine closure for coal and lignite mines.PIB
- Defined timelines at different stages of scrutiny and approval make decisions time-bound.PIB
- Escrow-based funding of mine closure works: claims are reimbursed from the escrow account within one month of receipt, with test-checking of claims, and five-yearly claims are verified by a wider set of agencies.PIB
- Underground coal gasification: recognised as a mining method, with its own 2026 mining plan guidelines made part of this framework.PIB
- Flexibility for project proponents in line with prevailing conditions, to speed up operationalisation of mines.PIB
- Promotes scientific mine closure and repurposing of closed mine land for the benefit of local communities.PIB
Static GK
- Ministry of Coal: headquartered in New Delhi, responsible for exploration of coal and lignite reserves and for production, supply, distribution and price of coal.
- Coal India Limited: state-owned coal miner headquartered in Kolkata, operating under the administrative control of the Ministry of Coal; the largest coal producer in the world by output.
- Mines and Minerals (Development and Regulation) Act, 1957: the basic framework of mining regulation in India, applicable to all minerals except minor and atomic minerals.
- Coal Mines (Nationalization) Act, 1973: all coal mines in India were nationalised in May 1973; the Coal Mines (Nationalization) Act, 1973 and the Coking Coal Mines (Nationalization) Act, 1972 were repealed in January 2018.
- Underground coal gasification (UCG): an in-situ process that converts coal in a non-mined seam into product gas (mainly methane, hydrogen, carbon monoxide and carbon dioxide) brought to the surface through production wells.
Achievements
- Sets defined timelines at different stages of scrutiny and approval, making decisions time-bound.PIB
- Cuts the escrow reimbursement period for mine closure works to one month from receipt of claim.PIB
- Brings underground coal gasification into the formal mine planning framework, giving a clear route for this method.PIB
Challenges
- Closure funding depends on timely verification of claims; a wider set of verifying agencies helps but needs consistent standards to avoid uneven checks.
- Mine closure and repurposing for local communities require coordination between the operator, the state government and local bodies, which a central framework alone cannot ensure.
- Faster approvals and greater flexibility for project proponents must be balanced with environmental and safety checks in the mine planning process.
Way forward
- Outcome monitoring of approval timelines and escrow reimbursements, so that the one-month target is tracked in practice.
- Handholding of project proponents, especially new entrants, in preparing mining and closure plans under the new timelines.
- Convergence with state governments and local bodies so that closed mine land is repurposed for community benefit.
Timeline
20 December 2026
The guidelines come into force, 30 days from the date of issue.PIB
23 November 2026
Ministry of Coal issued the 2026 guidelines for mining and mine closure plans for coal and lignite mines, cutting escrow reimbursement for closure works to one month, widening verification agencies, and recognising underground coal gasification as a mining method.
Read the storyJanuary 2018
The Coal Mines (Nationalization) Act, 1973 and the Coking Coal Mines (Nationalization) Act, 1972 were repealed.
May 1973
All coal mines in India were nationalised under the Coal Mines (Nationalization) Act, 1973.
Every new story on this subject is added here automatically.
Frequently asked questions
When do the 2026 mining and mine closure guidelines come into force?
The guidelines come into force 30 days from the date of issue, which was 20 November 2026, so from about 20 December 2026.PIB
How long does escrow reimbursement for mine closure works now take?
The reimbursement period has been reduced to one month from the receipt of a claim, with provision for test-check of claims.PIB
Is underground coal gasification recognised under these guidelines?
Yes, the guidelines recognise underground coal gasification as a mining method and make the 2026 UCG mining plan guidelines an integral part of the framework.PIB
GS paper mapping
- GS-2Government policies and interventions for development in various sectors; Mining and related regulation
- GS-3Energy: conventional and non-conventional sources; Environment impact of mining and mine closure
- GS-3Infrastructure: energy; ease of doing business for industry
Sources
Every fact on this page was checked against these pages.