Sivok-Rangpo New Line Railway Project: complete guide

A 45-km broad-gauge rail line under construction through West Bengal and Sikkim, meant to give Sikkim its first direct railway connection to the national network, for passengers, freight and tourism.

Updated: 28 November 20261 topicRailway

The Sivok-Rangpo line is a broad-gauge new line under construction that links Sivok, near Siliguri in West Bengal, with Rangpo in Sikkim.

The line is also seen as strategically important for national security, since it is expected to help troops and armaments move faster towards the Indo-Tibet border.

Its tunnels and bridges are built in Himalayan terrain, and the route runs through Mahananda Wildlife Sanctuary, which led to long delays in approval and construction.

Sivok-Rangpo New Line Railway Project: quick facts

Responsible ministry
Ministry of Railways
Tunnels
14 tunnels, about 86 per cent of the route length; Tunnel No. 10 (5.3 km) is the longest
Bridges
23

Key facts

Responsible ministryMinistry of RailwaysPIB
Tunnels14 tunnels, about 86 per cent of the route length; Tunnel No. 10 (5.3 km) is the longestPIB
Bridges23PIB
Construction contractorIRCON International, awarded the contract in May 2010
Revised completion targetDecember 2027 (as updated in May 2025)

Key features and how it works

  • The line passes through Darjeeling and Kalimpong districts in West Bengal and Pakyong district in Sikkim.PIB
  • Stations at Sivok, Riyang, Melli and Rangpo, plus an underground halt at Teesta Bazaar.PIB
  • At Sivok, the line connects with the existing New Jalpaiguri-Alipurduar railway route, linking Sikkim to the national network.PIB
  • The remaining work after excavation is tunnel lining, track laying and installation of railway safety systems.PIB
  • Planned extensions: a second phase from Rangpo to Gangtok and a third phase to Nathu La, with a Melli-Dentam fork towards West Sikkim.

Static GK

  • IRCON International: government company incorporated on 28 April 1976 under the Companies Act, 1956 (originally Indian Railway Construction Company Limited), a turnkey construction company in the public sector.ircon.org
  • Ministry of Railways: a ministry of the Government of India that runs Indian Railways; the Railway Board, which it constitutes, is housed in Rail Bhawan, New Delhi.
  • Indian gauge (1,676 mm, 5 ft 6 in): the broad gauge used for the Sivok-Rangpo line; it was adopted as India's standard gauge after the first passenger line between Bombay and Thane.

Comparison

Sivok-Rangpo vs Jammu-Baramulla line

BasisSivok-Rangpo lineJammu-Baramulla line
Length45 km (Wikipedia: 44.96 km)324 km
Gauge1,676 mm broad gauge1,676 mm broad gauge
StatusUnder construction; excavation of all 14 tunnels complete (Nov 2026)Fully operational as of 7 June 2025
Construction contractorIRCON International (contract May 2010)Indian Railways, Konkan Railway, IRCON and other contractors on different sections
CostNot stated in the sources opened (2008 estimate was INR 13.4 billion)INR 28,000 crore (2022, Wikipedia)

Achievements

  • Excavation was completed in all 14 tunnels, including the 5.3-km Tunnel No. 10 on 27 November 2026.PIB
  • In 2026 (February), the project was reported to be 90 per cent complete, with the Teesta Bazaar station almost finished.
  • The Supreme Court approved the project in February 2016 with strict guidelines from the National Wildlife Board.

Challenges

  • Forest and wildlife clearance delayed the route: the first 22 km pass through an elephant sanctuary, and the alignment had not been finalised by 2013 due to lack of approval.
  • The completion date has been pushed back several times, from December 2023 to August 2025 and then to December 2027, which also raised cost overruns over the 2008 estimate.
  • The Himalayan terrain is geologically challenging, so tunnel and bridge work is slow and risky.

Way forward

  • Track monitoring of progress against the revised deadline, so that tunnel lining and track laying do not slip further.
  • Wildlife safeguards, such as speed limits and animal tracking in the forest stretch, need to be enforced once trains run.
  • Convergence with the planned second and third phases (Gangtok and Nathu La) and the Melli-Dentam fork so that the network grows as one system.

Timeline

  1. 28 November 2026

    Excavation of all 14 tunnels is complete, with the 5.3-km Tunnel No. 10 breakthrough on 27 November 2026; tunnel lining, track laying and safety systems now follow.

    Read it in full
  2. January 2025

    Target completion extended to December 2027.

  3. May 2024

    Target completion extended to August 2025.

  4. November 2021

    Target completion extended to December 2023.

  5. February 2016

    Supreme Court of India approved the project with restrictions on speed and on tunnel digging (daytime only).

  6. June 2015

    National Wildlife Board cleared the project.

  7. May 2010

    IRCON International awarded the construction contract.

  8. October 2009

    Foundation stone laid by the Vice President of India.

Every new topic on this subject is added here automatically.

Frequently asked questions

Which ministry runs the Sivok-Rangpo line?

The Ministry of Railways is responsible for the project.PIB

Which tunnel is the longest on the line?

Tunnel No. 10 is the longest at 5.3 km, and its excavation was completed on 27 November 2026.PIB

Where does the line connect with the national network?

At Sivok, it connects with the existing New Jalpaiguri-Alipurduar railway route.PIB

GS paper mapping

  • GS-3Infrastructure: rail transport and connectivity, border infrastructure
  • GS-1Geography: Himalayan terrain and Sikkim (regional geography)
  • GS-2Government policies and interventions for development in the north-east, and connectivity
  • GS-3Environment: forest and wildlife clearance for infrastructure projects