The tunnel is intended to end the seasonal closure. Together with the Z-Morh Tunnel, it is meant to provide year-round connectivity, reduce travel time and improve armed forces logistics.
Key facts
| Parent ministry | Ministry of Road Transport and Highways (MoRTH)PIB |
|---|---|
| Tunnel length | 13.153 km tunnel; 17.030 km approach roads; 30.18 km total project lengthPIB |
| Purpose | All-weather road connectivity between Srinagar and Ladakh (Leh), on NH-1 |
| Height and width | 9.5 m wide, 7.57 m high; about 11,578 feet above sea levelHindustan |
| Project cost | Total project cost ₹6,809.69 crore (as stated in 2024 PIB release)PIB |
| Progress | About 70% construction complete (Gadkari, November 2026); excavation completed 9 JuneHindustan |
| Contractor | Megha Engineering & Infrastructure Ltd (MEIL), Hyderabad-based |
Key features and how it works
- Two-lane, bi-directional, single-tube horseshoe-shaped tunnel; the western portal is at Baltal (about 3,000 m) and the eastern portal at Meenamarg, towards Dras and Kargil.
- Designed as a smart tunnel with fully transverse ventilation, uninterrupted power supply, emergency lighting, CCTV, variable message signs, a tunnel radio system, emergency telephones and fire-fighting cabinets every 125 m, and cross-passages every 250 m.
- Built on engineering, procurement and construction (EPC) mode: the Government of India provides the funds, the executing agency builds the tunnel, and then hands it over to the Government.
- Expected to cut the crossing time of the Zojila Pass from about three hours to about 20 minutes, and ease civilian and military movement into Ladakh.hindustantimes.com
- The tunnel is one of 31 road tunnels being constructed: 20 in Jammu and Kashmir and 11 in Ladakh.
Static GK
- Ministry of Road Transport and Highways: the ministry that owns and monitors the project; its minister reports progress to Parliament.PIB
- Megha Engineering & Infrastructure Ltd (MEIL): Hyderabad-based contractor that took over the project in 2020 after the earlier contractor, IL&FS Transportation Networks Ltd, went bankrupt.
- NATM (New Austrian Tunnelling Method): the tunnelling method used on the Z-Morh Tunnel in view of fragile Himalayan geology.
Comparison
Zojila Tunnel vs Z-Morh (Sonamarg) Tunnel
| Basis | Zojila Tunnel | Z-Morh (Sonamarg) Tunnel |
|---|---|---|
| Length | 13.153 km | 6.5 km |
| Location | Zoji La pass, Sonamarg to Dras (Ladakh) | Gagangir to Sonamarg, Ganderbal district, J&K |
| Project cost | ₹6,809.69 crore (TPC, 2024 PIB) | ₹2,378 crore for balance work (Wikipedia; not confirmed on official page) |
| Status | Under construction; completion February 2028 | Operational; inaugurated January 2025 (HT) |
| Contract model | EPC mode, Government funds | DBFOT annuity concession by NHIDCL |
Achievements
- Excavation of the 13.153 km tunnel was completed on 9 June, and about 70% of construction was complete by November 2026.Hindustan
- The project employed 1,141 people.hindustantimes.com
- Once complete, the tunnel will give year-round road access to Ladakh, which at present has weather-related closures of about five months a year on the Srinagar-Leh and Manali-Leh roads.hindustantimes.com
Challenges
- Contractor change: the original contractor, IL&FS Transportation Networks Ltd, went bankrupt, which forced fresh bids and a new contract to MEIL in 2020.
- Fragile Himalayan terrain and landslide risk, which the minister himself flagged at WLF-7 as needing careful planning of geology, hydrology and slope stability.Hindustan
Way forward
- Outcome monitoring: a time-bound progress review at each milestone, given the repeated revisions of the completion date.
- Environment and slope safety: long-term monitoring of slopes and hydrology along the approach roads, in line with the minister's call to balance development and environmental protection.Hindustan
- Convergence with the Z-Morh tunnel and approach roads so that the whole Srinagar-Leh corridor works as one all-weather link.
Timeline
24 November 2026
Union Minister Nitin Gadkari said at WLF-7 that about 70% of Zojila Tunnel construction is complete, with completion expected in six to eight months.
Read the story9 June 2026
Excavation (breakthrough) of the tunnel completed.Hindustan
31 July 2025
Gadkari told Lok Sabha that the project was 64% complete and ₹3,934.42 crore had been spent.hindustantimes.com
8 August 2024
Written reply in Lok Sabha: physical progress 52.13%; scheduled completion 29 September 2026.PIB
2020
MEIL was awarded the construction contract after the earlier contractor went bankrupt.
May 2018
Prime Minister Narendra Modi laid the foundation stone and construction started.
2013
Cabinet approved the Zoji-La and Z-Morh road tunnel projects.
Every new story on this subject is added here automatically.
Frequently asked questions
How long is the Zojila Tunnel?
The Zojila Tunnel is 13.153 km long.PIB
Which ministry is building the Zojila Tunnel?
The Ministry of Road Transport and Highways is responsible for the project.PIB
Which company is building the Zojila Tunnel?
Megha Engineering & Infrastructure Ltd (MEIL) is the contractor, having been awarded the work in 2020.
GS paper mapping
- GS-1Geography: Himalayan terrain, mountain passes and landslide-prone regions
- GS-2Governance and Government schemes: infrastructure projects and their monitoring; connectivity to border regions
- GS-3Infrastructure: roads and tunnels; disaster management and landslides
- GS-4Ethics: balancing development and environmental protection in fragile ecosystems