The policy aims to encourage setting up CBG plants, bio-diesel plants and bio-coal plants that use bio-energy waste, and it sits alongside incentives available from the Government of India. The state's nodal agency for the policy is UPNEDA, under the Department of Additional Sources of Energy.invest.up.gov.in
The Cabinet amendment answers a planning problem: the earlier rule allowed at most one plant in each tehsil, so new plants were blocked even where existing plants were small and bio-waste was still available. The amendment ties the number of plants to the assessed production capacity of each district and tehsil.Hindustan
Uttar Pradesh State Bio-Energy Policy 2022: quick facts
- Policy name
- Uttar Pradesh State Bio-Energy Policy 2022 (declared by the state government in September 2022)
- Nodal agency
- UPNEDA, Department of Additional Sources of Energy, Government of Uttar Pradesh
- CBG incentive
- ₹75 lakh per tonne, up to a maximum of ₹20 crore, for a compressed biogas plant
Key facts
| Policy name | Uttar Pradesh State Bio-Energy Policy 2022 (declared by the state government in September 2022)invest.up.gov.in |
|---|---|
| Nodal agency | UPNEDA, Department of Additional Sources of Energy, Government of Uttar Pradeshinvest.up.gov.in |
| CBG incentive | ₹75 lakh per tonne, up to a maximum of ₹20 crore, for a compressed biogas plantinvest.up.gov.in |
| Bio-coal incentive | ₹75,000 per tonne, up to a maximum of ₹20 crore, for a bio-coal plantinvest.up.gov.in |
| Bio-diesel incentive | ₹3 lakh, up to a maximum of ₹20 crore, for a bio-diesel plant.invest.up.gov.in |
| Active CBG plants | 42 active CBG plants producing 350 tonnes of biogasHindustan |
| Assessed capacity | 2,250 tonnes per day CBG and 8,000 tonnes per day bio-coalHindustan |
Key features and how it works
- Incentive for CBG plants: ₹75 lakh per tonne of capacity, up to ₹20 crore, in addition to central government incentives.invest.up.gov.in
- Incentive for bio-coal plants: ₹75,000 per tonne, up to ₹20 crore; for bio-diesel plants: ₹3 lakh, up to ₹20 crore.invest.up.gov.in
- Equipment subsidy: 30% of cost, maximum ₹20 lakh, on boiler, Recker and trolley equipment, in addition to the 50% central subsidy under the agriculture mechanisation scheme.invest.up.gov.in
- Infrastructure support: subsidy on construction of an approach road of up to 5 km, with maximum investment of ₹50 crore.invest.up.gov.in
- Other concessions: 100% exemption from stamp duty and electricity duty, and government land on lease at ₹1 per acre per year for bio-energy industry and feedstock storage.invest.up.gov.in
- Amendment (2026): the one-plant-per-tehsil limit is removed and plant numbers are approved on the basis of assessed district and tehsil production capacity.Hindustan
Static GK
- Invest UP: the state's investment promotion portal, which hosts the policy documents, GOs and the Bio-energy Enterprises Promotion Programme 2022 page.invest.up.gov.in
- GOBARdhan Portal: A portal listed under the Ministry of Petroleum and Natural Gas.gobardhan.gov.in
Achievements
- The state reports 42 active CBG plants producing 350 tonnes of biogas, and an assessed CBG capacity of 2,250 tonnes per day.Hindustan
- The policy gives state-level capital and land incentives that go beyond central incentives, which makes it a strong pull for private bio-energy investment.
Challenges
- Earlier rules capped each tehsil at one plant, which blocked new capacity even where bio-waste was still unused.Hindustan
- Plant numbers depend on accurate district and tehsil capacity assessments, so errors in bio-waste estimates can misdirect approvals.
- Bio-energy plants depend on steady feedstock supply, so the sector faces the risk that units start but cannot run at full capacity.
Way forward
- Track the number of approved plants against assessed capacity in each district and tehsil to check that the amendment is working.
- Link the state incentives with central schemes and the GOBARdhan registration process so investors can complete approvals in one route.
- Support plant owners with feedstock planning and handholding so new units run at their assessed capacity.
Timeline
18 November 2026
Cabinet amends the policy to remove the one-plant-per-tehsil limit; future plant approvals will be based on assessed district and tehsil bio-waste production capacity.
Read the story19 October 2024
A GO on a partial amendment to the revenue system for smooth setup of projects under the policy is listed. The Hindi policy document was last updated on October 19, 2024.invest.up.gov.in
13 April 2023
Several GOs on implementation, amendment, stamp duty and the Public Works Department provisions of the policy were issued.invest.up.gov.in
10 November 2022
English version of the Uttar Pradesh State Bio-Energy Policy-2022 was published.invest.up.gov.in
September 2022
The Government of Uttar Pradesh declared the Bio-Energy Policy 2022.invest.up.gov.in
Every new story on this subject is added here automatically.
Frequently asked questions
What does the UP Bio-Energy Policy 2022 offer for a CBG plant?
It offers an incentive of ₹75 lakh per tonne of capacity, up to a maximum of ₹20 crore, for setting up a compressed biogas plant.invest.up.gov.in
Which agency is the nodal agency for the policy?
UPNEDA, under the Department of Additional Sources of Energy, is the nodal agency for the policy.invest.up.gov.in
GS paper mapping
- GS-3Energy: renewable energy, bio-energy and CBG; conservation and sustainable use of resources
- GS-2Government policies and interventions; state government schemes and incentives for industry
- GS-3Waste management and circular economy (bio-waste to energy)
Sources
Every fact on this page was checked against these pages.