For Prelims: Paimana Portal, Cost Overrun, Mega Project
For Mains: Economy: Infrastructure and Project Management; Governance: Monitoring and Evaluation of Government Schemes
Source:Dainik Bhaskar
5 facts for one-day exams
SSC, railway, police and teaching exams ask direct questions like these.
- The Paimana Portal monitors central government infrastructure projects.
- Total cost overrun on 1,853 projects is ₹3.22 lakh crore.
- 25 mega projects account for ₹2.11 lakh crore (65%) of total cost overrun.
- Hubli-Ankola rail line in Karnataka is 25 years behind schedule.
- The Land Acquisition Act, 2013 reduced opposition to land acquisition by ensuring fair compensation.
The news
The central government's Paimana Portal, in its October 2026 report, has revealed that 1,853 ongoing infrastructure projects have seen a total cost overrun of ₹3.22 lakh crore. Of this, just 25 mega projects account for ₹2.11 lakh crore, or 65% of the total increase. The report states that this amount could have built over 4,200 schools at ₹50 crore each, or more than 1,400 hospitals at ₹150 crore each.
The worst-affected project is the Hubli-Ankola rail line in Karnataka, which was to be completed by March 2005 but now has a revised target of March 2030 — a delay of 25 years. Hydropower projects such as Subansiri and Tapovan-Vishnugad are over 16 years behind schedule. The report notes that 1,360 projects are on time or within two years of delay, indicating that the problem is concentrated in large, complex projects.
According to Harion Sharma, former chief of the PWD, delays are often caused by changes in government priorities and funding issues when a new government takes over, though such instances are now limited. The report says that since the 2013 land acquisition law ensured fair compensation, opposition has reduced. Competitive tendering has enabled many projects to be built at 10-15% below their approved budgets, and a multi-level monitoring system is expected to further reduce delays and cost overruns.
Why in the news?
The Paimana Portal's October 2026 report has quantified the massive cost overrun on central infrastructure projects, with 25 mega projects alone accounting for ₹2.11 lakh crore in cost overruns, highlighting a persistent fiscal and governance challenge.
What is the 2013 land acquisition law?
The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 replaced the colonial-era Land Acquisition Act of 1894. It came into force on 1 January 2014. The law mandates higher compensation, up to four times the market value in rural areas, and requires consent from at least 70% of affected families for public-private projects and 80% for private projects. It also includes comprehensive rehabilitation and resettlement provisions for those displaced.
What is the Paimana Portal?
The Paimana Portal is a central government online platform that monitors the progress and cost of infrastructure projects across ministries. It provides real-time data on project timelines and cost overruns, and its periodic reports are used to assess the health of the country's infrastructure pipeline.
What are the causes and effects of the delays?
The report and experts point to land acquisition, environmental clearances, and policy changes with new governments as key causes of delay. The 2013 Land Acquisition Act has reduced opposition by ensuring fair compensation, but large projects still face administrative hurdles. The opportunity cost is significant: the ₹2.11 lakh crore overrun on 25 projects could have built over 4,200 schools or 1,400 hospitals. However, the report also notes that competitive tendering has enabled many projects to be built at 10-15% below their approved budgets, and 1,360 projects are on time or within two years of delay.
What is the next step to reduce delays?
The report indicates that a multi-level monitoring system is expected to further reduce delays and cost overruns in the future. Projects are now executed in two phases: first, land acquisition and environmental/forest clearances are obtained, and then construction begins, which is intended to streamline execution.
Facts and terms for exams
- Paimana Portal:
- A central government online platform for monitoring the progress and cost of infrastructure projects. It provides real-time data on project timelines and cost overruns.
- Cost Overrun:
- The amount by which the actual cost of a project exceeds its original budgeted cost. It is usually expressed in absolute terms or as a percentage of the original cost.
- Mega Project:
- A large-scale infrastructure project typically costing ₹1,000 crore or more. These projects involve multiple stakeholders and complex execution processes.
Why it matters for exams
Exams: UPSC, SSC
Syllabus: Economy: Infrastructure and Project Management; Governance: Monitoring and Evaluation of Government Schemes
Common mistake: Examiners may swap the total cost overrun (₹3.22 lakh crore) with the overrun on just the 25 mega projects (₹2.11 lakh crore), or vice versa. They may also ask about the number of projects (1,853) as a direct fact. Remember: 25 mega projects account for 65% of the total cost overrun.
Mains question
The Paimana Portal report reveals that 25 mega projects account for 65% of the total cost overrun on central infrastructure. Examine the systemic causes of such delays and their fiscal implications.
Stuck? Get it in one tap
The Paimana Portal is a government website that tracks how much large projects cost and whether they finish on time. Its latest report says 1,853 projects have gone over budget by ₹3.22 lakh crore. Just 25 very big projects account for ₹2.11 lakh crore of this extra cost, which is enough money to build over 4,200 schools.
- The Paimana Portal monitors central government infrastructure projects.
- Total cost overrun on 1,853 projects is ₹3.22 lakh crore.
- 25 mega projects account for ₹2.11 lakh crore (65%) of total cost overrun.
- Hubli-Ankola rail line in Karnataka is 25 years behind schedule.
- The Land Acquisition Act, 2013 reduced opposition to land acquisition by ensuring fair compensation.
- Economy: Infrastructure and Project Management
- Governance: Monitoring and Evaluation of Government Schemes
Related concepts: Paimana Portal, Cost Overrun, Mega Project
Practice questions
Pick an answer, then read the explanation.
- Q1Hard
Consider the following statements regarding the Paimana Portal report (October 2026):
- 1.The total cost overrun on 1,853 ongoing central projects is ₹3.22 lakh crore.
- 2.The 25 mega projects account for 50% of the total cost overrun.
- 3.The Hubli-Ankola rail line in Karnataka is 25 years behind schedule.
Which of the statements given above is/are correct?
Explanation: Statement 1 is correct: the total cost overrun is ₹3.22 lakh crore. Statement 2 is incorrect: the 25 mega projects account for 65% (not 50%) of the total cost overrun. Statement 3 is correct: the Hubli-Ankola rail line is 25 years behind its original schedule. Hence option C is correct.
- Q2Medium
According to the Paimana Portal report, how many schools (at ₹50 crore each) could have been built with the cost overrun on just the 25 mega projects?
Explanation: The cost overrun on 25 mega projects is ₹2.11 lakh crore. At ₹50 crore per school, this amount could build over 4,200 schools (₹2,11,000 crore / ₹50 crore = 4,220). The other options are mathematical miscalculations of the same division.
- Q3Medium
What is the primary consequence of cost overruns in central infrastructure projects as highlighted by the Paimana Portal report?
Explanation: The report explicitly states that the ₹2.11 lakh crore overrun could have built 4,200 schools or 1,400 hospitals, highlighting the opportunity cost. While cost overruns can increase fiscal deficit, the report's main emphasis is on what could have been achieved with that money.
Frequently asked questions
1. What is the Paimana Portal?
The Paimana Portal is a central government online platform that monitors the progress and cost of infrastructure projects across ministries.
2. What is the total cost overrun on central projects as per the October 2026 report?
The total cost overrun on 1,853 ongoing central projects is ₹3.22 lakh crore.
3. Which project is the most delayed according to the report?
The Hubli-Ankola rail line in Karnataka is the most delayed, being 25 years behind its original schedule.
4. How many schools could have been built with the cost overrun on 25 mega projects?
Over 4,200 schools (at ₹50 crore each) could have been built with the ₹2.11 lakh crore cost overrun.