₹2.11 Lakh Crore Cost Overrun on 25 Mega Projects, Paimana Portal Report Reveals

11 November 20262 min1 source3 questionsStory 14 of 24

For Prelims: Paimana Portal, Cost Overrun, Mega Project

For Mains: Economy: Infrastructure and Project Management; Governance: Monitoring and Evaluation of Government Schemes

Source:Dainik BhaskarDainik Bhaskar

The news

The central government's Paimana Portal, in its October 2026 report, has revealed that 1,853 ongoing infrastructure projects have seen a total cost overrun of ₹3.22 lakh crore. Of this, just 25 mega projects account for ₹2.11 lakh crore, or 65% of the total increase. The report states that this amount could have built over 4,200 schools at ₹50 crore each, or more than 1,400 hospitals at ₹150 crore each.

The worst-affected project is the Hubli-Ankola rail line in Karnataka, which was to be completed by March 2005 but now has a revised target of March 2030 — a delay of 25 years. Hydropower projects such as Subansiri and Tapovan-Vishnugad are over 16 years behind schedule. The report notes that 1,360 projects are on time or within two years of delay, indicating that the problem is concentrated in large, complex projects.

According to Harion Sharma, former chief of the PWD, delays are often caused by changes in government priorities and funding issues when a new government takes over, though such instances are now limited. The report says that since the 2013 land acquisition law ensured fair compensation, opposition has reduced. Competitive tendering has enabled many projects to be built at 10-15% below their approved budgets, and a multi-level monitoring system is expected to further reduce delays and cost overruns.

Why in the news?

The Paimana Portal's October 2026 report has quantified the massive cost overrun on central infrastructure projects, with 25 mega projects alone accounting for ₹2.11 lakh crore in cost overruns, highlighting a persistent fiscal and governance challenge.

What is the 2013 land acquisition law?

The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 replaced the colonial-era Land Acquisition Act of 1894. It came into force on 1 January 2014. The law mandates higher compensation, up to four times the market value in rural areas, and requires consent from at least 70% of affected families for public-private projects and 80% for private projects. It also includes comprehensive rehabilitation and resettlement provisions for those displaced.

What is the Paimana Portal?

The Paimana Portal is a central government online platform that monitors the progress and cost of infrastructure projects across ministries. It provides real-time data on project timelines and cost overruns, and its periodic reports are used to assess the health of the country's infrastructure pipeline.

What are the causes and effects of the delays?

The report and experts point to land acquisition, environmental clearances, and policy changes with new governments as key causes of delay. The 2013 Land Acquisition Act has reduced opposition by ensuring fair compensation, but large projects still face administrative hurdles. The opportunity cost is significant: the ₹2.11 lakh crore overrun on 25 projects could have built over 4,200 schools or 1,400 hospitals. However, the report also notes that competitive tendering has enabled many projects to be built at 10-15% below their approved budgets, and 1,360 projects are on time or within two years of delay.

What is the next step to reduce delays?

The report indicates that a multi-level monitoring system is expected to further reduce delays and cost overruns in the future. Projects are now executed in two phases: first, land acquisition and environmental/forest clearances are obtained, and then construction begins, which is intended to streamline execution.

Facts and terms for exams

Paimana Portal:
A central government online platform for monitoring the progress and cost of infrastructure projects. It provides real-time data on project timelines and cost overruns.
Cost Overrun:
The amount by which the actual cost of a project exceeds its original budgeted cost. It is usually expressed in absolute terms or as a percentage of the original cost.
Mega Project:
A large-scale infrastructure project typically costing ₹1,000 crore or more. These projects involve multiple stakeholders and complex execution processes.

Why it matters for exams

Exams: UPSC, SSC

Syllabus: Economy: Infrastructure and Project Management; Governance: Monitoring and Evaluation of Government Schemes

Common mistake: Examiners may swap the total cost overrun (₹3.22 lakh crore) with the overrun on just the 25 mega projects (₹2.11 lakh crore), or vice versa. They may also ask about the number of projects (1,853) as a direct fact. Remember: 25 mega projects account for 65% of the total cost overrun.

Mains question

The Paimana Portal report reveals that 25 mega projects account for 65% of the total cost overrun on central infrastructure. Examine the systemic causes of such delays and their fiscal implications.

Stuck? Get it in one tap

Practice questions

Pick an answer, then read the explanation.

  1. Q1Hard

    Consider the following statements regarding the Paimana Portal report (October 2026):

    1. 1.The total cost overrun on 1,853 ongoing central projects is ₹3.22 lakh crore.
    2. 2.The 25 mega projects account for 50% of the total cost overrun.
    3. 3.The Hubli-Ankola rail line in Karnataka is 25 years behind schedule.

    Which of the statements given above is/are correct?

  2. Q2Medium

    According to the Paimana Portal report, how many schools (at ₹50 crore each) could have been built with the cost overrun on just the 25 mega projects?

  3. Q3Medium

    What is the primary consequence of cost overruns in central infrastructure projects as highlighted by the Paimana Portal report?

Frequently asked questions

1. What is the Paimana Portal?

The Paimana Portal is a central government online platform that monitors the progress and cost of infrastructure projects across ministries.

2. What is the total cost overrun on central projects as per the October 2026 report?

The total cost overrun on 1,853 ongoing central projects is ₹3.22 lakh crore.

3. Which project is the most delayed according to the report?

The Hubli-Ankola rail line in Karnataka is the most delayed, being 25 years behind its original schedule.

4. How many schools could have been built with the cost overrun on 25 mega projects?

Over 4,200 schools (at ₹50 crore each) could have been built with the ₹2.11 lakh crore cost overrun.

All sources

Stories from the last 30 days on the same topic, state or exams

EconomyKarnatakaBank: Very important

ED raids CoinDCX and Delta Exchange in Bengaluru for FEMA violations

  • Agency Conducting Raid: Enforcement Directorate (ED)
  • Key Law Violated: Foreign Exchange Management Act (FEMA)
Background GK: FEMA (Foreign Exchange Management Act)FEMA, 1999; SEBI Act, 1992; RBI Act, 1934Nodal: Enforcement Directorate (ED)Don't make this mistake!
4 questions · 2 minDainik Bhaskar
EconomyKarnataka

Karnataka alleges 31.2% ethanol in petrol, OMCs deny E20 violation

  • Alleged ethanol percentage in petrol: 26% to 31.2% (Karnataka claim)
  • Mandated ethanol blending limit (E20): 20%
Background GK: Ethanol Blending (E20)IS 17021 (BIS standard)Nodal: Ministry of Petroleum and Natural GasDon't make this mistake!
4 questions · 2 minHindustanIndian Express
EconomyUPSC: Important

GSI to undertake 300 critical mineral projects in 2026-27

  • Nodal Ministry: Ministry of Mines
  • Projects completed since 2014: 4,373 total (1,724 critical minerals, 656 rare earth elements)
Background GK: Geological Survey of India (GSI)Nodal: Ministry of MinesDon't make this mistake!
4 questions · 2 minThe Hindu
EconomyUPSC: Very important

PLFS Q3 2026: LFPR rises to 55.5%, rural UR falls to 4.3%

  • Nodal Ministry: Ministry of Statistics and Programme Implementation (MoSPI)
  • Survey Name: Periodic Labour Force Survey (PLFS)
Background GK: Labour Force Participation Rate (LFPR)Nodal: Ministry of Statistics and Programme ImplementationDon't make this mistake!
4 questions · 2 minPIB
EconomyBank: Very important

NPCI to levy MDR on UPI payments above ₹2,000

  • Nodal Body: National Payments Corporation of India (NPCI)
  • Full Form of MDR: Merchant Discount Rate
Background GK: Merchant Discount Rate (MDR)Nodal: National Payments Corporation of India (NPCI)Don't make this mistake!
4 questions · 2 minHindustanDainik Bhaskar