Tags:EnvironmentUPSC
Source:PIB
Subject: Indian Economy and Environment (Energy, Renewable Energy Targets)|Target exams: UPSC
Key points for Prelims: Wind power capacity, Viability Gap Funding, Contracts for Difference mechanism, Renewable Purchase Obligations, National Institute of Wind Energy
Mains syllabus mapping
- General Studies Paper 3: Energy: renewable energy sources, wind and offshore wind, grid integration and storage, Renewable Purchase Obligations, infrastructure
- General Studies Paper 2: Government policies and interventions for development, role of the Ministry of New and Renewable Energy, India-UK collaboration on offshore wind
Key facts for one-day exams
- India ranked fourth globally in installed wind power capacity.
- The National Institute of Wind Energy installed more than 900 wind-monitoring stations.
- India’s installed wind capacity stood at 59.20 GW on 30 September 2026.
- The 2036 wind capacity target is 156 GW.
- Madhya Pradesh’s estimated wind potential at 150 metres is 55.4 GW.
India wind energy capacity and targets: why in the news?
India’s installed wind energy capacity stood at 59.20 GW on 30 September 2026. The government has set targets of 100 GW by 2030 and 156 GW by 2036.
India’s installed wind power capacity stood at 59.20 GW as of 30 September 2026, accounting for about 19.8% of the country’s total installed renewable energy capacity of 299.25 GW, according to a backgrounder published by the Press Information Bureau. The government has set targets of 100 GW of wind capacity by 2030 and 156 GW by 2036. Between March 2014 and September 2026, installed wind capacity grew from 21 GW to 59.20 GW, a nearly 2.8-fold increase.
India generated 106.7 billion units of wind power in FY 2025-26 and recorded its highest-ever annual wind capacity addition of 6.05 GW during the year, surpassing the previous record of 5.4 GW in 2016-17. Nearly 45% of wind generation occurs during peak demand hours, complementing solar power. An additional 28 GW of wind capacity is under implementation. India ranks fourth globally in installed wind power capacity.
The government has approved ₹6,853 crore in viability gap funding for 1,000 MW of offshore wind projects, comprising 500 MW each off the coasts of Gujarat and Tamil Nadu. A 500 MW pilot project has been launched under the Contracts for Difference mechanism, designed to reduce price volatility and provide revenue certainty to developers. A task force was constituted in January 2026 to address regulatory, land, transmission and implementation challenges. A dedicated wind component has been introduced under Renewable Purchase Obligations to ensure sustained demand.
When was the National Institute of Wind Energy established?
The National Institute of Wind Energy was established in 1998 in Chennai. NIWE is an autonomous institution under the Ministry of New and Renewable Energy. The Renewable Purchase Obligation mechanism was introduced under the Electricity Act, 2003.
What is India’s wind resource potential?
India’s estimated gross wind power potential is 695.5 GW at 120 metres and 1,163.9 GW at 150 metres above ground level. At 150 metres, the assessed potential is concentrated in eight states: Rajasthan (284.2 GW), Gujarat (180.8 GW), Maharashtra (173.9 GW), Karnataka (169.3 GW), Andhra Pradesh (123.3 GW), Tamil Nadu (95.1 GW), Madhya Pradesh (55.4 GW) and Telangana (54.7 GW). More than 900 wind-monitoring stations have been installed nationwide by the National Institute of Wind Energy to map resources and identify high-potential sites.
How has manufacturing and indigenisation progressed?
Wind turbine manufacturing capacity has increased from 10 GW in 2014 to about 24 GW as of March 2026. The sector has achieved 70-80% indigenisation across key components, with strong domestic supply chains for blades, towers, gearboxes and other critical equipment. The Approved List of Models and Manufacturers, transparent bidding guidelines and Late Payment Surcharge Rules have strengthened investor confidence.
What are the priorities and global partnerships?
Priorities include expanding wind deployment into emerging states such as Madhya Pradesh, Telangana and Odisha; launching India’s offshore wind sector through identified leasing areas; integrating wind into round-the-clock renewable energy solutions through storage-linked business models; and deploying AI-based forecasting tools. India is strengthening wind energy cooperation with the UK, Denmark, Belgium, Germany and the European Union. The India-UK Offshore Wind Taskforce was launched in February 2026 under Vision 2035. A cooperation agreement with Denmark was signed in 2019 and the bilateral MoU was renewed in May 2025.
Wind potential at different hub heights
| Hub height | Estimated gross potential |
|---|---|
| 120 metres | 695.5 GW |
| 150 metres | 1,163.9 GW |
Key terms
- Installed capacity:
- The maximum rated power output of generating equipment, expressed in units such as MW or GW.
- Viability Gap Funding:
- Financial support intended to make projects that face a viability gap more feasible.
- Renewable Purchase Obligation:
- A requirement for specified obligated entities to procure a prescribed share of electricity from renewable sources.
- Contracts for Difference:
- A contractual mechanism designed to reduce price volatility and provide revenue certainty to renewable energy developers.
India wind energy capacity and targets: why it matters for exams
Exams: UPSC
Syllabus: Environment: Renewable energy and climate mitigation; Economy: Energy infrastructure and energy security
Common mistake: Examiners may present 1,163.9 GW of estimated potential as installed capacity; installed wind capacity was 59.20 GW on 30 September 2026.
Mains practice questions
Question 1(GS-3 | 250 words | 15 marks)
Despite a record annual addition of 6.05 GW and a rising installed base of 59.20 GW, India's wind energy sector faces structural challenges that could slow progress toward the 2030 target of 100 GW. Critically examine the challenges and suggest measures to bridge the gap.
Answer outline
- Introduction: Open by noting that India's wind capacity has grown nearly 2.8-fold since 2014 to 59.20 GW and recorded its highest-ever annual addition in FY 2025-26, yet the 100 GW target for 2030 still requires a sharp acceleration.
- Body:
- Scale of the gap: the target implies adding far more capacity in the remaining years than the record pace achieved so far, with 28 GW already under implementation.
- Land and siting constraints: wind projects need large contiguous land and face competing land use, local resistance and clearance delays.
- Transmission and grid integration: wind resources in Rajasthan and other states must be linked to load centres, and curtailment risks arise without adequate transmission and storage.
- Offshore wind challenges: high costs, untested regulatory frameworks and port, supply chain and marine infrastructure needs, which the task force and CfD pilot seek to address.
- Financing and price risk: price volatility and revenue uncertainty deter developers, partly addressed by Contracts for Difference and viability gap funding.
- Conclusion: A balanced way forward combines faster land and transmission planning, stable long-term revenue mechanisms and sustained demand through Renewable Purchase Obligations, so that the 2030 and 2036 targets are backed by institutional reform as well as capacity addition.
Question 2(GS-3 | 150 words | 10 marks)
Wind power complements solar power by generating a substantial share during peak demand hours. Discuss the role of wind energy in achieving India's renewable energy goals and the policy instruments needed to ensure its sustained growth.
Answer outline
- Introduction: Note that wind supplied 106.7 billion units in FY 2025-26 and that nearly 45% of wind generation occurs during peak demand hours, making it a valuable partner to solar.
- Body:
- Complementarity with solar: wind and solar output profiles differ, improving overall grid reliability and reducing dependence on fossil-fuel peaking plants.
- Share of renewables: wind accounts for about 19.8% of India's 299.25 GW renewable capacity, contributing to diversification of the energy mix.
- Policy instruments: Renewable Purchase Obligations with a dedicated wind component create assured demand.
- Financial instruments: viability gap funding and Contracts for Difference reduce price risk and attract investment, especially offshore.
- Conclusion: Wind energy's complementarity with solar makes it central to a stable renewable grid, and sustained growth depends on combining demand assurance with financial and regulatory support.
Stuck? Get it in one tap
Wind turbines use moving air to generate electricity. Installed capacity measures the rated power a system can produce, while wind potential estimates the resource available for future projects. India is supporting offshore projects and improving grids to expand wind energy.
- Environment: Renewable energy and climate mitigation
- Economy: Energy infrastructure and energy security
Related concepts: Installed capacity, Viability Gap Funding, Renewable Purchase Obligation, Contracts for Difference
Practice questions
Pick an answer, then read the explanation.
- Q1Easy
Which Indian ministry is responsible for renewable energy development, including wind power?
Explanation: The Ministry of New and Renewable Energy is the nodal ministry for renewable energy development. The other ministries have distinct responsibilities in power, finance and external affairs.
- Q2Hard
Consider the following statements about India’s wind energy sector:
- 1. India’s installed wind capacity was 59.20 GW on 30 September 2026.
- 2. India’s 2036 wind capacity target is 100 GW.
- 3. Approved offshore viability gap funding covers 500 MW each off Gujarat and Tamil Nadu.
Which of the statements given above is/are correct?
Explanation: Statements 1 and 3 are correct: installed capacity was 59.20 GW and the offshore allocation is equally divided between the two states. Statement 2 is incorrect: the 2036 target is 156 GW, while 100 GW is the 2030 target.
- Q3Medium
What was India’s estimated gross wind power potential at 150 metres above ground level?
Explanation: Estimated gross wind potential at 150 metres is 1,163.9 GW. The 695.5 GW estimate corresponds to 120 metres; the other values are not the stated 150-metre estimate.
- Q4Medium
What is the intended purpose of the 500 MW Contracts for Difference pilot in wind energy?
Explanation: Contracts for Difference are designed to reduce price volatility and provide revenue certainty to renewable energy developers. Resource mapping, transmission development and capacity targets address different aspects of the wind sector.
Frequently asked questions
1. What is India’s wind energy target for 2030?
The target is 100 GW of wind capacity by 2030.
2. How much offshore wind funding has India approved?
₹6,853 crore has been approved for 1,000 MW of offshore wind projects.
3. Which state has the highest assessed wind potential at 150 metres?
Rajasthan has an estimated 284.2 GW of wind potential at 150 metres.
4. How much wind capacity did India add in 2025-26?
India added a record 6.05 GW of wind capacity in FY 2025-26.