Gurugram Metro Rail Limited (GMRL) - Old Gurugram Metro (Metro Corridor Millennium City Centre to Cyber City): complete guide

The Old Gurugram Metro is a 28.5 km elevated metro corridor from Millennium City Centre to DLF Cyber City, being built by Gurugram Metro Rail Limited (GMRL) to connect Old and New Gurugram, and is useful for UPSC, state PSC and SSC aspirants studying urban transport and PPP/JV metro projects.

Updated: 16 November 20261 storyHPSC HCSHSSC

The Old Gurugram Metro is a new rapid transit corridor meant to connect the older residential and commercial areas of Gurugram with the new commercial hubs of Cyber City and the Dwarka Expressway. It is separate from the already operating Rapid Metro, which serves the DLF area and links to the Delhi Metro at Sikanderpur.

The project is being built in two civil works phases: Phase I from Millennium City Centre to Sector 9, and Phase II from Sector 9 to Cyber City. Phase I is under construction and its tender has been allotted. Phase II is the stage now moving to preparation.Hindustan

The corridor aims to integrate Old and New Gurugram, which are divided by NH 48, and to link residential, institutional and commercial areas with Udyog Vihar, Cyber City and the transit-oriented development zone along the Dwarka Expressway.gmrl.org.in

Gurugram Metro Rail Limited (GMRL) - Old Gurugram Metro (Metro Corridor Millennium City Centre to Cyber City): quick facts

Implementing body
Gurugram Metro Rail Limited (GMRL), a 50:50 joint venture of the Government of India and the Government of Haryana, created in February 2024
Cabinet approval
Union Cabinet approved the Millennium City Centre to Cyber City metro corridor on 7 June 2023
Stations and depot
27 elevated stations (26 on the main corridor, 1 on the spur) and one depot

Key facts

Implementing bodyGurugram Metro Rail Limited (GMRL), a 50:50 joint venture of the Government of India and the Government of Haryana, created in February 2024
Cabinet approvalUnion Cabinet approved the Millennium City Centre to Cyber City metro corridor on 7 June 2023
Stations and depot27 elevated stations (26 on the main corridor, 1 on the spur) and one depotgmrl.org.in
Phase II tenderAbout ₹1,662 crore; opening scheduled for 18 November 2026; construction envisaged within 30 monthsHindustan
Estimated costOriginal estimate ₹5,452.72 crore, later revised to ₹10,266.54 crore
Gauge and powerStandard gauge (1,435 mm); elevated

Key features and how it works

  • Corridor: 28.5 km elevated metro from Millennium City Centre (formerly HUDA City Centre) to Cyber City, with a 1.85 km spur towards Dwarka Expressway.gmrl.org.in
  • Phase I runs Millennium City Centre to Sector 9; Phase II runs Sector 9 to Cyber City. Each civil works phase is delivered separately, and a depot and utility relocation works are planned alongside.
  • Phase II proposed stations: Sector 7, Sector 4, Sector 5, Railway Station, Ashok Vihar, Sector 3, Bajghera Road, Palam Vihar Extension, Palam Vihar and Sector 23A.Hindustan
  • Interchanges are planned with the Delhi Metro Yellow Line, the railway station, bus depot, Rapid Metro and the proposed RRTS corridor.gmrl.org.in
  • GMRL is a joint venture with 50:50 equity contributions from the Government of India and the Government of Haryana.gmrl.org.in
  • Phase II construction requires use of the median of existing roads, with a road width of about nine metres needed. Encroachments are to be cleared, utility lines shifted and traffic diversion planned in advance.Hindustan

Static GK

  • The Haryana Urban Development Authority Act, 1977, established HUDA on 30 April 1977. On 1 June 2017, the Haryana cabinet decided to rename it HSVP.
  • Rapid Metro Gurgaon: the first fully privately financed light metro in India, operated by DMRC on behalf of HMRTC; operation and maintenance being transferred to GMRL from September 2025.

Comparison

Old Gurugram Metro vs Rapid Metro Gurgaon vs Pune Metro

BasisOld Gurugram MetroRapid Metro GurgaonPune Metro
Length28.5 km corridor (26.65 km + 1.85 km spur)12.85 km, 11 stations56.3 km across three lines (as of November 2026)
Implementing or operating bodyGMRL, 50:50 GoI and GoH joint ventureRapid MetroRail Gurgaon Ltd (built); operated by DMRC for HMRTCMahaMetro (Purple and Aqua lines), PMRDA on PPP basis (Line 3)
Funding modelPublic joint venture (GoI and GoH equity)Fully private financing (PPP concession)Public joint venture (state and central) for Lines 1 and 2; PPP for Line 3
Launch or approvalCabinet approval 7 June 2023; GMRL created February 2024First phase opened 14 November 2013Inaugurated 6 March 2022; final central approval 7 December 2016
CostRevised estimated cost ₹10,266.54 crorePhase I construction cost ₹1,088 crore (some reports ₹1,450 crore)Phase 1 estimated cost ₹11,420 crore

Achievements

  • The Union Cabinet approved the 28.5 km corridor in June 2023, moving the project to the implementation stage.
  • Phase I construction is underway and its tender has been allotted, while Phase II tender worth about ₹1,662 crore has been floated.Hindustan
  • GMRL is taking over Rapid Metro operations from DMRC, bringing both networks under one agency.

Challenges

  • Road encroachments and illegal constructions along the route must be cleared before the median can be used, which can slow the start of Phase II.Hindustan
  • Shifting water, sewer, gas and electricity lines under live urban roads adds time and coordination cost.
  • The cost has risen from the original estimate, which shows the risk of cost overrun in a long urban corridor.

Way forward

  • Joint monitoring of road measurement and encroachment clearance between GMRL and HSVP, with a dated handover of the route.
  • Advance traffic diversion plans and utility shifting schedules to keep the 30-month construction window.Hindustan
  • Integration with the Delhi Metro Yellow Line, the railway station and the RRTS corridor to make the network useful for commuters.gmrl.org.in

Timeline

  1. 16 November 2026

    GMRL asked HSVP to measure roads and clear encroachments for Phase II; the ₹1,662 crore tender was issued 5 October 2026 and opens 18 November 2026.

    Read the story
  2. 5 October 2026

    GMRL issues the Phase II tender worth about ₹1,662 crore.Hindustan

  3. September 2025

    HMRTC initiates the transfer of Rapid Metro operation and maintenance to GMRL.

  4. 2025

    Line 2 of the Gurgaon Metro is under construction.

  5. February 2024

    Gurugram Metro Rail Limited (GMRL) is created as a 50:50 GoI and GoH joint venture.

  6. 7 June 2023

    Union Cabinet approves the Millennium City Centre to Cyber City metro corridor with a spur to Dwarka Expressway.

Every new story on this subject is added here automatically.

Frequently asked questions

Who is implementing the Old Gurugram Metro?

Gurugram Metro Rail Limited (GMRL), a 50:50 joint venture of the Government of India and the Government of Haryana, is implementing the Millennium City Centre to Cyber City corridor.gmrl.org.in

When did the Union Cabinet approve the Gurugram metro corridor?

The Union Cabinet approved the 28.5 km Millennium City Centre to Cyber City corridor on 7 June 2023.

How long is the Phase II construction period?

Phase II, from Sector 9 to Cyber City, is planned to be built within 30 months after its tender of about ₹1,662 crore is awarded.Hindustan

GS paper mapping

  • GS-3Infrastructure: urban transport, metro rail and PPP/JV financing
  • GS-2Governance: role of state urban development agencies (HSVP) and central-state joint ventures
  • GS-1Urbanisation: problems of Old and New Gurugram and urban transport

Sources

Every fact on this page was checked against these pages.

  1. Hindustan
  2. gmrl.org.in

Latest stories on this subject