Source:
Hindustan
Subject: Infrastructure (Urban Transport) and Urban Governance|Target exams: HPSC HCS, HSSC
Key points for Prelims: Gurugram Metro Rail Limited (GMRL), Haryana Shahari Vikas Pradhikaran (HSVP), Old Gurugram Metro Phase II, Median of roads for metro construction, Right of way and encroachment removal
Mains syllabus mapping
- General Studies Paper 3: Infrastructure: urban transport, metro rail projects, land acquisition and right of way
- General Studies Paper 2: Functions and responsibilities of the Union and States; urban governance and inter-agency coordination
Gurugram Metro Rail Limited (GMRL) - Old Gurugram Metro (Metro Corridor Millennium City Centre to Cyber City): quick facts
- Implementing body
- Gurugram Metro Rail Limited (GMRL), a 50:50 joint venture of the Government of India and the Government of Haryana, created in February 2024
- Cabinet approval
- Union Cabinet approved the Millennium City Centre to Cyber City metro corridor on 7 June 2023
- Stations and depot
- 27 elevated stations (26 on the main corridor, 1 on the spur) and one depot
Key facts for one-day exams
- Old Gurugram Metro Phase II is planned between Sector 9 and DLF Cyber City.
- The Phase II tender is worth approximately ₹1,662 crore.
- The tender is scheduled to open on 18 November 2026.
- The planned Phase II construction period is 30 months.
- Approximately nine metres of road width will be needed for construction.
Old Gurugram Metro Phase II: why in the news?
GMRL has formally requested HSVP to measure roads for Phase II of the Old Gurugram Metro, signalling the start of preparatory work for the ₹1,662 crore project between Sector 9 and DLF Cyber City.
Gurugram Metro Rail Limited (GMRL) has begun preparations for the second phase of the Old Gurugram Metro, requesting the Haryana Shahari Vikas Pradhikaran (HSVP) to measure roads along the route and share a report. The Phase II tender, worth approximately ₹1,662 crore, was issued on 5 October 2026 and is scheduled to be opened on 18 November 2026. Construction is envisaged within 30 months.
GMRL Chief Project Manager Gabdu Ram Chaudhary has written to HSVP officials stating that the metro construction requires the median of existing roads, with a road width of about nine metres needed. After road measurement, illegal constructions and encroachments are to be removed. GMRL has asked HSVP to free these roads of encroachments, as encroachments could cause difficulties for vehicle movement. Advance planning for traffic diversion and relocation of water, sewer, gas and electricity lines is also to be undertaken.
The proposed stations on Phase II include Sector 7, Sector 4, Sector 5, Railway Station, Ashok Vihar, Sector 3, Bajghera Road, Palam Vihar Extension, Palam Vihar and Sector 23A. Phase I of the Old Gurugram Metro, from Millennium City Centre metro station to Sector 9, is under construction and its tender has been allotted.
Key features and how it works
- Corridor: 28.5 km elevated metro from Millennium City Centre (formerly HUDA City Centre) to Cyber City, with a 1.85 km spur towards Dwarka Expressway.gmrl.org.in
- Phase I runs Millennium City Centre to Sector 9; Phase II runs Sector 9 to Cyber City. Each civil works phase is delivered separately, and a depot and utility relocation works are planned alongside.
- Phase II proposed stations: Sector 7, Sector 4, Sector 5, Railway Station, Ashok Vihar, Sector 3, Bajghera Road, Palam Vihar Extension, Palam Vihar and Sector 23A.
- Interchanges are planned with the Delhi Metro Yellow Line, the railway station, bus depot, Rapid Metro and the proposed RRTS corridor.gmrl.org.in
- GMRL is a joint venture with 50:50 equity contributions from the Government of India and the Government of Haryana.gmrl.org.in
- Phase II construction requires use of the median of existing roads, with a road width of about nine metres needed. Encroachments are to be cleared, utility lines shifted and traffic diversion planned in advance.
Related Static GK and comparison
- The Haryana Urban Development Authority Act, 1977, established HUDA on 30 April 1977. On 1 June 2017, the Haryana cabinet decided to rename it HSVP.
- Rapid Metro Gurgaon: the first fully privately financed light metro in India, operated by DMRC on behalf of HMRTC; operation and maintenance being transferred to GMRL from September 2025.
Old Gurugram Metro vs Rapid Metro Gurgaon vs Pune Metro
| Basis | Old Gurugram Metro | Rapid Metro Gurgaon | Pune Metro |
|---|---|---|---|
| Length | 28.5 km corridor (26.65 km + 1.85 km spur) | 12.85 km, 11 stations | 56.3 km across three lines (as of November 2026) |
| Implementing or operating body | GMRL, 50:50 GoI and GoH joint venture | Rapid MetroRail Gurgaon Ltd (built); operated by DMRC for HMRTC | MahaMetro (Purple and Aqua lines), PMRDA on PPP basis (Line 3) |
| Funding model | Public joint venture (GoI and GoH equity) | Fully private financing (PPP concession) | Public joint venture (state and central) for Lines 1 and 2; PPP for Line 3 |
| Launch or approval | Cabinet approval 7 June 2023; GMRL created February 2024 | First phase opened 14 November 2013 | Inaugurated 6 March 2022; final central approval 7 December 2016 |
| Cost | Revised estimated cost ₹10,266.54 crore | Phase I construction cost ₹1,088 crore (some reports ₹1,450 crore) | Phase 1 estimated cost ₹11,420 crore |
Achievements
- The Union Cabinet approved the 28.5 km corridor in June 2023, moving the project to the implementation stage.
- Phase I construction is underway and its tender has been allotted, while Phase II tender worth about ₹1,662 crore has been floated.
- GMRL is taking over Rapid Metro operations from DMRC, bringing both networks under one agency.
Challenges
- Road encroachments and illegal constructions along the route must be cleared before the median can be used, which can slow the start of Phase II.
- Shifting water, sewer, gas and electricity lines under live urban roads adds time and coordination cost.
- The cost has risen from the original estimate, which shows the risk of cost overrun in a long urban corridor.
Way forward
- Joint monitoring of road measurement and encroachment clearance between GMRL and HSVP, with a dated handover of the route.
- Advance traffic diversion plans and utility shifting schedules to keep the 30-month construction window.
- Integration with the Delhi Metro Yellow Line, the railway station and the RRTS corridor to make the network useful for commuters.gmrl.org.in
Old Gurugram Metro: Phase I and Phase II
| Feature | Phase I | Phase II |
|---|---|---|
| Route | Millennium City Centre to Sector 9 | Sector 9 to DLF Cyber City |
| Tender status | Allotted | Issued; opening scheduled |
Haryana connection
Key terms
- Metro rail:
- A metro rail system is an urban rail transport system designed to carry passengers within a metropolitan area.
- Tender:
- A tender is a formal process through which an organisation invites bids for specified work, goods or services.
- Utility relocation:
- Utility relocation means shifting existing service infrastructure, such as water pipes or electricity lines, to accommodate construction.
Old Gurugram Metro Phase II: why it matters for exams
Exams: HPSC HCS, HSSC
Syllabus: Economy: Urban infrastructure and transport; Governance: Urban planning and public services
Common mistake: Examiners may present Phase II as the Millennium City Centre-Sector 9 section; that is Phase I, while Phase II is planned from Sector 9 to DLF Cyber City.
Mains practice questions
Question 1(GS-3 | 250 words | 15 marks)
Urban metro rail projects in cities such as Gurugram face delays due to encroachments and the need to reallocate road space. Critically examine the challenges in executing metro projects on existing city roads and suggest measures to address them.
Answer outline
- Introduction: Open by noting that the Old Gurugram Metro Phase II, a roughly ₹1,662 crore project, requires GMRL to use the median of existing roads, which makes the removal of encroachments and coordination with HSVP a precondition for construction.
- Body:
- Land and right of way: metro construction on existing roads needs a road width of about 9 metres, so the median must be freed, and this exposes the difficulty of acquiring road space in dense urban areas.
- Encroachments and illegal constructions: they must be cleared before work begins, and their presence can delay the project and create hurdles for vehicle movement.
- Utility shifting: relocation of water, sewer, gas and electricity lines requires advance planning and coordination among multiple agencies, adding time and cost.
- Traffic management: diverting traffic during construction on a busy corridor such as the route towards DLF Cyber City demands detailed planning to minimise public inconvenience.
- Institutional coordination: the division of responsibility between the metro corporation (GMRL) and the urban development authority (HSVP) can slow decisions unless roles and timelines are clearly defined.
- Conclusion: A balanced way forward lies in integrated planning from the design stage, time-bound inter-agency coordination, and firm enforcement against encroachments, so that metro expansion proceeds without sacrificing urban mobility or public welfare.
Question 2(GS-2 | 150 words | 10 marks)
Discuss how the coordination between a metro rail corporation and an urban development authority can shape the timely execution of urban transport projects, with reference to the planned Phase II of the Old Gurugram Metro.
Answer outline
- Introduction: Introduce the Old Gurugram Metro Phase II and the request by GMRL to HSVP for road measurement and encroachment clearance as an example of inter-agency dependence in urban infrastructure.
- Body:
- Role of GMRL: the metro corporation plans construction, tendering and stations, including the proposed stops from Sector 7 to Sector 23A.
- Role of HSVP: the urban development authority controls road measurement and enforcement of encroachment removal, making it a critical partner.
- Benefits of coordination: clear division of responsibility, shared planning for traffic diversion and utility relocation, and faster approvals.
- Risks of weak coordination: delays in clearing encroachments and utility shifting can push project timelines beyond the planned 30 months.
- Conclusion: Effective, time-bound coordination between metro and urban authorities, supported by a clear institutional framework, is essential to deliver urban transport projects on schedule.
Stuck? Get it in one tap
Old Gurugram Metro Phase II is a planned rail connection from Sector 9 to DLF Cyber City. Authorities need to measure roads and plan the shifting of service lines before construction. The tender is scheduled to be opened on 18 November 2026.
- Economy: Urban infrastructure and transport
- Governance: Urban planning and public services
Related concepts: Metro rail, Tender, Utility relocation
Practice questions
Pick an answer, then read the explanation.
- Q1Easy
Which body requested road measurements for Old Gurugram Metro Phase II?
Explanation: Gurugram Metro Rail Limited requested the road measurements. Haryana Shahari Vikas Pradhikaran was asked to conduct them; the other bodies were not the requesting organisation.
- Q2Hard
Consider the following statements about Old Gurugram Metro:
- 1.Phase I runs from Millennium City Centre metro station to Sector 9.
- 2.Phase II is planned from Sector 9 to DLF Cyber City.
- 3.The Phase II tender was allotted before its scheduled opening on 18 November 2026.
Which of the statements given above is/are correct?
Explanation: Statements 1 and 2 correctly identify the two route sections. Statement 3 is incorrect: the Phase II tender was scheduled to open on 18 November 2026; the allotted tender was for Phase I.
- Q3Medium
What is the approximate tender value for Old Gurugram Metro Phase II?
Explanation: The Phase II tender is valued at approximately ₹1,662 crore. The other amounts do not match that tender value.
- Q4Medium
Why has Gurugram Metro Rail Limited requested road measurements for Old Gurugram Metro Phase II?
Explanation: Road measurements will help assess the space needed for construction and identify encroachments. The request concerns route preparation, not fare setting, Phase I tender allocation or replacement of the metro.
Frequently asked questions
1. What is the planned route of Old Gurugram Metro Phase II?
Phase II is planned from Sector 9 to DLF Cyber City.
2. When is the Old Gurugram Metro Phase II tender scheduled to open?
The tender is scheduled to open on 18 November 2026.
3. Which stations are planned on Old Gurugram Metro Phase II?
Planned stations include Sector 7, Sector 4, Sector 5, Railway Station, Ashok Vihar, Sector 3, Bajghera Road, Palam Vihar Extension, Palam Vihar and Sector 23A.
4. Why were road measurements requested for Old Gurugram Metro Phase II?
Road measurement will help assess construction space and identify encroachments along the proposed route.